PRINCE2 Process Level: MP Managing Product
Delivery
Details:
Ø
responsibility lies with the Team
Manager Ø
encompasses the following
responsibilities of the Team Manager, these are to: o
ensure work is authorised and
agreed o
accept and check Work Package o
create a Team Plan o
ensure work progress and forecasts
are assessed Ø
basic objectives: o
agree the Work Package with the
Project Manager o
get the work done o
hand back the completed work Sub-processes:Sub-processes
in Managing Product Delivery are: Ø
MP1 Accepting a Work Package Ø
MP2 Executing a Work Package Ø
MP3 Delivering a Work Package
|
Send mail to Anthony.Cairns@AnthonyCairns.com with
questions or comments about this web site.
|